Subcontractor insurance: what to ask for and how to check a certificate

Ask a subcontractor for employers’ liability insurance and public liability insurance, and for professional indemnity insurance if they design anything. Employers’ liability is the only one the law requires, for at least £5 million. The other two are normally required by your subcontract, which sets the limits. On every certificate read four things: the name, the dates, the limit and what is covered and excluded.

Updated 16 November 2026

Drop a certificate or schedule into the register and it is read for you: the name, the insurer, the limit, the dates and any exclusion that touches the job, set against the start date and the limit in your order. You decide whether to accept it.

Check a subcontractor

Employers’ liability insurance

Most employers must hold employers’ liability insurance by law, for at least £5 million and from an authorised insurer. The £5 million includes costs, and it can be made up of more than one policy. In practice most policies are written for £10 million. An employer without it can be fined £2,500 for every day it is uninsured, and up to £1,000 for not displaying the certificate or refusing to show it to an inspector.

The duty is the subcontractor’s, not yours. You check it because their employees will be working on your site, and an uninsured claim is a problem for everyone on the job.

A firm with no employees does not need it, and there are a few narrow exemptions. Whether someone counts as an employee for this purpose depends on how they work, not on what they are called. A firm that directs labour-only workers day to day may well need the cover even if it treats them as self-employed. If a subcontractor tells you they do not need employers’ liability, ask for that in writing, signed.

A company in a group may be covered by a policy in the parent’s name. That is fine if the certificate or schedule shows the cover extends to the company you are placing the order with. If it does not say so, ask the broker to confirm it.

Public liability insurance

No law requires public liability insurance. It covers injury to other people and damage to other people’s property. Your subcontract sets the limit, and the place to start is the limit in your own contract with the client.

Check both the limit and the cover. The limit is the easy part. The part that goes wrong is the cover. A policy written for a decorator may exclude work above a set height. A roofer’s policy may exclude or restrict hot works. Read the business description and the exclusions against the work they are coming to do.

Check your own policy too. Many contractors’ public liability policies carry a condition that you check your subcontractors hold their own cover. If yours does and you have not checked, a claim arising from their work could be yours to pay.

Professional indemnity insurance

Ask for professional indemnity insurance when the subcontractor designs any part of what it installs: a steel fabricator sizing connections, a mechanical contractor designing the system, a cladding installer working up the fixings.

Professional indemnity is written on a claims-made basis: the policy that answers is the one in force when the claim is made, not when the design was done. That is why subcontracts ask for it to be kept up for years after the job. Check the limit, the dates, and what your order says about keeping it in place.

Three more things matter on a claims-made policy. The retroactive date: design done before it is not covered. The exclusions: some policies exclude or cap cover for fire safety and cladding. And notification: a claim or a circumstance must be reported to the insurer in the policy period. Ask the subcontractor or their broker about each if the design matters to your job.

How to read a certificate

Whichever policy it is, check the same things in the same order.

  • The name. It must name the company you are placing the order with, or be a group policy that covers it. A sister company’s policy, or a trading name you cannot connect to the company, is not enough.
  • The dates. It must already be in force on the day they start, and you should know the day it runs out.
  • The limit. For public liability, the limit for any one event. Compare it with the figure in your order.
  • The business description. Does it describe the trade they are carrying out for you?
  • The exclusions and conditions. Look for height or depth limits, hot works, and work on particular kinds of building.
  • The insurer. A UK insurer or its agent should be on the Financial Services Register.

Certificates, schedules and broker letters

An employers’ liability certificate is a document the law prescribes. For public liability and professional indemnity there is no such thing: you will be sent a policy schedule, or a letter from the broker headed “to whom it may concern”.

A broker’s letter is a summary. It often leaves out the exclusions. If the work is high risk, such as work at height, hot works or deep excavation, ask for the schedule and the relevant endorsements as well.

The date that matters is the one during the job

Most policies renew annually, and a job often runs across the renewal. A certificate that was in date when you placed the order can expire in week six.

Keep the expiry date beside each policy and ask for the renewal a month before. A subcontractor who cannot produce it has usually renewed and not sent it, but you should not have to assume that.

Sources

Written for England, Scotland and Wales. CDM 2015 and the employers’ liability law apply across Great Britain. The Building Regulations duty described here is England’s; Wales has had its own dutyholder regulations since July 2026, and Scotland and Northern Ireland have their own building standards. Northern Ireland also has its own CDM regulations and employers’ liability law.

This page is general information, not legal or insurance advice. Check the legal requirements, your subcontract and your insurer’s conditions for your own job.