Subcontractor pre-start checklist

Before a subcontractor starts on your site, check six things: employers’ liability insurance, public liability insurance, a safety scheme certificate, cards for the people coming, proof they can do this work, and professional indemnity insurance if they design. Insurance and scheme certificates must name the company, or a group policy that covers it, and be in force on the day they start. Cards and training records belong to the people being sent. Two of the six rest on law. The others come from your contract or from common practice, and it helps to know which is which.

Updated 16 November 2026

The register on this site lists these six checks for each subcontractor, keeps the expiry date beside each one and tells you whose checks are complete and what is still needed.

Check a subcontractor

The six checks

The register on this site works through these six for each subcontractor.

What to ask a subcontractor for before they start, and what asks for it
CheckAsk forLook atAsked for by
Employers’ liability insuranceThe current certificate, or a signed note of why they are exemptNames the company, or a group policy that covers it; in force on the start date; at least £5 millionLaw, for most employers
Public liability insuranceThe schedule or a broker’s letterNames the company; in force on the start date; the limit for any one event; whether the cover and its exclusions fit this jobYour subcontract
Safety scheme certificateA current certificate from an SSIP member scheme (such as CHAS, SMAS or Once For All Health & Safety) or the Common Assessment StandardNames the company; in date; the work categories cover this jobIndustry practice
CardsA list of who is coming, with each person’s cardEach person’s own card; in date; the right occupation for the job they will do; checked electronicallyIndustry practice
Proof they can do this workSupervisor and gang training, and one or two similar jobs, or your own experience of themWhether it fits the work on this job, not work in generalLaw: you must take reasonable steps
Professional indemnity insuranceThe schedule, only if they designNames the company; in force; covers this kind of design; the limit your order asks for; the retroactive dateYour subcontract

A scheme certificate is not a job check

A safety scheme or Common Assessment Standard certificate says the company was assessed against a set standard, usually within the last year. It is good evidence that the firm can organise its health and safety. On its own it does not establish that they are suitable for the roof you are asking them to work on, with the gang they are sending.

So keep the two apart. The certificate covers the company in general. The pre-start check asks whether you hold what you need from this company for this job, on this date.

What the law asks of you

Under CDM 2015, anyone who appoints a contractor must take reasonable steps to satisfy themselves that the contractor has the skills, knowledge, experience and, for a company, the organisational capability to do the work safely. That is regulation 8. It applies to a main contractor appointing a subcontractor as much as to a client appointing a main contractor.

In England, the Building Regulations add a second duty for building work. Before you let anyone carry out building work you must take all reasonable steps to satisfy yourself that they are competent to do it in line with the regulations. That is regulation 11E, in force since October 2023. For work on a higher-risk building you must also ask whether a serious sanction, such as a compliance notice, a stop notice or a relevant conviction, has been imposed on them in the last five years.

Wales has had its own equivalent dutyholder and competence rules since 1 July 2026. Check the Welsh Government’s guidance for work there.

Neither regulation names a certificate, a card or a questionnaire. They ask for reasonable steps, in proportion to the work. A written record of what you checked is how you show you took them.

Also settle these before they start

These are not in the register, but they belong on the same list.

  • Verify them with HMRC under the Construction Industry Scheme before you pay them for the first time. HMRC tells you whether to deduct 20%, 30% or nothing.
  • Review their RAMS for this job. A method statement written for another site is a common reason to send one back.
  • Check any plant they bring: the examination and inspection records that apply to that equipment, and who does the daily checks.
  • Book their site induction. On a job with more than one contractor, the principal contractor must make sure a suitable induction is given.
  • Have the signed subcontract order, with the insurance limits written in it. The order is what you hold the certificates against.

When to check

Ask when you place the order, so nothing is requested the night before. Check again in the week before they start, because that is when a renewal date gets missed. Then look at the dates once a month while they are on site: insurance that was in date at the start can expire before the job finishes.

A check that has expired should stop being a tick. That is the point of keeping the expiry date beside each one.

Keep a record

Keep what you were sent, who accepted it and on what date. If something goes wrong on site, that record shows the steps you took before the company started.

For higher-risk building work in England the regulations go further: whoever makes an appointment must give the client a written record of the steps they took to check competence, and the client must keep it (regulation 11D(10)).

Sources

Written for England, Scotland and Wales. CDM 2015 and the employers’ liability law apply across Great Britain. The Building Regulations duty described here is England’s; Wales has had its own dutyholder regulations since July 2026, and Scotland and Northern Ireland have their own building standards. Northern Ireland also has its own CDM regulations and employers’ liability law.

This page is general information, not legal or insurance advice. Check the legal requirements, your subcontract and your insurer’s conditions for your own job.